Case studies

Achievement of a new cogeneration unit at Titan CHPP

Short description:

ISPE, as investor, prepared the feasibility study for the „Green/Brown Field” project, consisting in the implementation of a new, high efficiency unit within CHPP Titan, as follows: gas turbine of about 13 MW, and heat recovery hot water boiler of 20 Gcal/h, (out of which 5 Gcal/h supplementary firing). The new cogeneration unit will be located in the available space in the precinct of Titan CHPP which will ensure based on contract the following utilities: softened water, demineralized water, cooling water, fire fighting water, drinking water, taking over of tap and industrial water and will provide a supporting connection in a 6 kV cell.

Services offered:

Feasibility Study including: technical analysis, investment appraisal, economical efficiency analysis, sensibility analysis, general layout, etc.

Estimated technical performances:

Annual average performances:

Annual fuel consumption:41342 tce/year, out of which:

Overall efficiency, (in accordance with Directive 2004/8/EC): 80.77%
Primary fuel savings, (in accordance with Directive 2004/8/EC): 15.42%.

Estimated economic efficiency:

Economic efficiency analysis shows that cash flow is positive,during the operating period

Country and location:

Romania, Bucharest, Titan CHPP

Client:

ENINVEST S.A.

Date of project :

2007
 